Infrasource News Project Spotlight: Creek Gas Main Replacement

Project Spotlight: Creek Gas Main Replacement

Published on Back To Index

Natural Gas

In a remarkable feat of engineering and coordination, our crew successfully completed a jack and bore operation to cross a creek. This critical project involved the installation of 1,150 feet of gas main to replace the existing pipeline, which needed to be relocated to accommodate a new bridge construction.

The installation included approximately 150 feet of 8-inch coated steel inserted through a 12-inch steel casing, with 8-inch HDPE (High-Density Polyethylene) on either side to tie into the existing infrastructure. This meticulous process ensured the new facilities were clear of all new bridge footings, with the jack and bore operation conducted at a depth of 23 feet beneath the creek bed.

Despite encountering significant rock during excavation, our team extended daily work hours and did weekend work to keep the project on schedule. Their dedication and flexibility were crucial in meeting the project’s deadlines and ensuring the contract with the bridge contractor remained on track.

This project serves as a testament to our team’s unwavering commitment to excellence and our ability to overcome challenges. We are proud of the hard work and dedication demonstrated by everyone involved.

Recommended Posts

Back to Index
Projects
Project Spotlight: Plymouth 138/147 Mainstem Replacement

December 12, 2024 InfraSource has successfully delivered various solutions to the Electric Distribution and Transmission industry, and our team brings over 100 years of combined experience installing underground...

Learn More
Projects
Project Spotlight: Coy Road Widening & Gas Main Relocation

December 5, 2024 This newer project we worked on was located in Oregon, a suburb of Toledo, Ohio. The city of Oregon needed assistance replacing two gas lines...

Learn More
Back to Top